At Completion Cost is Different from Budgeted Total Cost 2 months 4 weeks ago #535

  • Anonymous
  • Anonymous's Avatar Topic Author
Hi Guys,

I have the following problem: In my schedule at completion cost is different than budgeted total cost . The cost is increased at completion cost from budgeted cost. How to solve this?

Thanks

At Completion Cost is Different from Budgeted Total Cost 2 months 4 weeks ago #537

  • Mohamad Ali
  • Mohamad Ali's Avatar Topic Author
Hi

Go to Projects click on the calculations tab on the rigth under resource assignments

make sure that under

When updating actual Units or Costs that

Subtract Actual from At Completion is checked

If it is checked

put in the actual then adjust the at completion make it equal the budgted costs