TOPIC: How to Show two or more currencies for a Project in Primavera P6?

How to Show two or more currencies for a Project in Primavera P6? 2 months 3 weeks ago #532

  • Abdel Khader Planner
  • Abdel Khader Planner's Avatar Topic Author
Hi All
Can we show two or more currencies for a Project in Primavera P6?

How to Show two or more currencies for a Project in Primavera P6? 2 months 3 weeks ago #533

  • Naomi Twirld
  • Naomi Twirld's Avatar Topic Author
I recommend you to create a UDF

Go to Enterprise, then User Defined Fields

in the drop down select Activities

then select Add

then select type in Foreign Costs in the title and in the data type select Cost

now for each activity add your foreign costs here