TOPIC: Resource Creep

Resource Creep 2 months 3 weeks ago #528

  • Amendo Nirosa
  • Amendo Nirosa's Avatar Topic Author
When I scheduled my schedule, it shows the resource dates outside the book ends of the activity they are assigned to, e.g. and activity could be 1st Jan to 10th Jan, say you claim 50% schedule the prograham on a week it pushes the resoure allocation past the remaining end date of the activity, anybody help with this please.

Thank You

Resource Creep 2 months 3 weeks ago #529

  • Toby Turnock
  • Toby Turnock's Avatar Topic Author
Hi Amendos

Please check the Project Details, Resources: is the "Drive activity/task dates by default" activated or not?

If not, resources may work longer than the task duration