TOPIC: Determining Max Units / Time for Resource Leveling

Determining Max Units / Time for Resource Leveling 2 months 4 weeks ago #524

  • Amadov Nicolet
  • Amadov Nicolet's Avatar Topic Author
Hi All

I want to know how to determine the Max Units/time, when leveling the resources? Say, in the resource usage profile, the time scale is set to Month/week.

Determining Max Units / Time for Resource Leveling 2 months 4 weeks ago #525

  • Anonymous
  • Anonymous's Avatar Topic Author
Hi Amadov

When you are making your resource dictionary in units & prices tab you can enter a value of max units/time according to this value the prog will determine overallocation .

for example : if u have 6 excavators and your time unit is day then max units/time = 6

if at any time u assign more than 6 units/time even for more than one activity you need to level your resources