TOPIC: How to model cure time in Microsoft Project?

How to model cure time in Microsoft Project? 5 months 3 weeks ago #636

  • Anonymous
  • Anonymous's Avatar Topic Author
Hi All

I wanted to know isit possible to model cure time for concrete in Microsoft Project using an elapsed time lag.
Thank you for your replies.

How to model cure time in Microsoft Project? 5 months 3 weeks ago #637

  • Jimmy Cart
  • Jimmy Cart's Avatar Topic Author
Hi
Yes it is possible. Here's how to model cure time as a separate task using standard hours and a 7-day work week