Hi all, is there a way to add a single predecessor to multiple tasks? I need a method for this because I don't have to go through and add it one by one.

How to Add Predecessor to Multiple Tasks in Microsoft Project? 3 months 1 day ago #620

  • Anonymous
  • Anonymous's Avatar Topic Author
Here is how

1. Organize/filter your schedule so that all 50 predecessors are located together.
2. Add the Successors column to your task table.
3. Enter the ID of the desired successor into the successors list of the first of the 50 predecessors..
4. Select the cell you just entered, then use the autofill cursor (black square at lower right corner of cell) to pull the successor ID into each of the remaining 49 predecessors. (If predecessors are not adjacent, then use copy/paste, though you'll need to paste 49 times.)

This won't work if your predecessors already have other successors and your intent is to add a new one. In that case dump the successors column to Excel, manipulate by concatenating strings, then copy/paste back to Microsoft Project.